News List

Press Enter to show all options, press Tab go to next option

Meredith Drive Reconstruction Project

Update 7/19/19: The remaining wires on existing power poles near NW 169th Street are expected to be transferred to the relocated poles by the middle of next week, allowing MidAmerican Energy to remove the old poles. This will allow the grading contractor to move back in and complete grading operations west of NW 167th Street. If dry conditions persist, filling and rough grading in these areas should be completed next week. Underground utility subcontractors will be on-site afterward to continue with the installation of storm sewer and water main in these same areas. As a result, additional activity and construction equipment working in the ROW west of NW 167th Street in the near term will occur.

Update 6/28/19: Rock subbase material is expected to be laid next week on the east half of the project prior to the start of paving operations. The Contractor is hopeful to be paving by mid-July on this end of the project. Utility and grading operations on the west half of the project will resume once all lines are transferred from existing power poles onto the relocated power poles by private utility companies.

Update 6/14/19: NW 167th Street will be closed at Meredith Drive after 8:00 am next Monday, June 17th while crews lay water main across this side street.  As a result, affected residents should use NW 169th Street for access onto and off of Meredith Drive next Monday.  The resulting trench will be backfilled with rock and reopened by the end of the day.  Changeable Message Boards are in place to notify affected residents and the traveling public of this upcoming closure.

Update 6/7/19: The Contractor is expecting to complete subgrade construction and testing on the east half of the project next week prior to placing rock subbase.  Paving on this half of the project is expected to follow before the end of the month.  In the coming weeks, the grading subcontractor will move to the west end of the project and begin filling operations in the south right-of-way allowing additional storm sewer and water main construction to occur. 

Update 5/24/2019: Progress was hampered this week due to persistent rains.  Finish grading and placement of rock subbase will proceed on the east half of the project as conditions allow. The storm sewer cross run completed under a temporary closure this past Wednesday on the west end of the project between NW 169th and NW 167th Streets allows for additional grading and utility work to occur in the south right-of-way.  As always, operations undertaken and progress made are highly dependent on additional rains predicted in the 10-day forecast.  

Update 5/20/2019:  Meredith Drive will be closed to through traffic between NW 167th Street and NW 169th Street this Wednesday, May 22, 2019, beginning at 8:30 a.m. to construct the storm sewer across Meredith Dr. The intersection of Meredith Dr. and NW 169th St. will remain open while this work is completed. Residents in the affected area should use Tanglewood Drive west to NW 169th St. to gain access to Meredith Dr. The Contractor has been allowed one day to complete work under this requested closure. Depending on how work proceeds, this section of roadway may still be closed during the evening commute home. This closure will allow for utility work on the west end of the project to continue in the coming weeks while paving starts on the east end of the project.

Update 5/3/2019: Utility work on the east half of the project (Phase 1) is nearing completion.  As a result, underground work in Phase 2 will continue next week with water main and storm sewer construction in the Right-of-Way (ROW) south of Meredith Drive between NW 164th and NW 167th Streets. These operations will require another closure of NW 164th St. at Meredith Dr. to construct the storm sewer across the side street. This work is currently scheduled to occur next Monday, May 6, 2019, as weather conditions allow. There will be a closure of NW 164th Street after 8:00 a.m. and reopen later the same day. Additional grading and filling operations and storm sewer outlet construction between NW 167th St. and Alice’s Road will also ramp up once remaining trees are removed early next week.

Update 4/30/2019: Construction has progressed over the last month on the east half of the project in Urbandale.  Relocation of utilities (private and public) is nearing completion on this Stage of construction with final grading and paving to follow.

In an attempt to keep the Underground Utility Subcontractor on-site and ultimately shorten the overall duration of the project, crews will be allowed to head west into Stage 2 with water main and storm sewer construction in the right-of-way.  While the Stage 2 sections of Meredith Drive will remain open to local traffic, these operations will require the temporary closure of side streets.  The first such closure is scheduled for this Wednesday, May 1st on NW 164th Street.  NW 164th Street will be closed at Meredith after 8:00 am while crews lay water main across the side street.  The resulting trench will be backfilled with rock and reopened by the end of the day.  Only one side street will be closed at a time during these operations.  As a result, affected residents may use either NW 167th Street or NW 169th Street to access Meredith Drive this Wednesday.  Changeable Message Boards are in place to notify affected residents and the traveling public of this upcoming closure.

This process will be repeated for both water main and storm sewer construction across NW 164th, NW 167th and NW 169th Streets in the coming weeks.  Again, only one side street will be closed at a time.  Please keep in mind that changes and delays in the proposed schedule (mainly weather related) are inevitable and will occasionally occur.

-- 

This project provides for the reconstruction of Meredith Drive from NW 156th Street to ¼ mile west of Alice’s Road as a four-lane roadway with left turn lanes including grading, water main, and storm sewer. The pavement will be Portland cement concrete with two 26-foot wide paving sections and a 28-foot grass median. The project scope also includes a 10-foot trail on the north side of the improved roadway and a 5-foot sidewalk on the south side. This is a joint project with the City of Urbandale. Concrete Technologies Inc. (CTI) has been hired by the Cities and will complete work in two separate stages of construction as shown in the exhibit below. For larger view of the staging areas, click >here.< It is anticipated that Meredith Drive will be reopened by the end of November 2019.

Please contact Clive Public Works at 223-6231 with questions, concerns, or the need for additional information.

Meredith Drive, street, reconstruction, construction, 2019

Return to full list >>
View Full Site